… In progressNZ First priority · National–NZ First agreement · Energy and resources
Examine transmission and connection pricing for new renewable generation.
What happened: The Electricity Authority has worked on network connection pricing: it set new distribution connection pricing rules in 2025 (in force from 1 April 2026), decided interim rules on up-front connection charges on 1 July 2026, and consulted on further reform from July to September 2026, alongside a separate paper on network pricing for distributed generation. No final decision specific to transmission or connection pricing for new renewable generation was found.
Official: Electricity Authority: Distribution connection pricing reform (project page, updated Oct 2026) Official: Electricity Authority: Reforming network pricing for distributed generation (paper) Official: Beehive: Statement of Government Policy to the Electricity Authority (Oct 2024)