✓ DoneNZ First priority · National–NZ First agreement · Housing and infrastructure
Progress the detailed business case for a dry dock at Marsden Point.
What happened: The detailed business case for a dry dock at Marsden Point was progressed in 2024: by 20 August 2024 a preferred option, location and concept design had been identified and Kānoa ran a market Request for Information. The project was then listed in Schedule 2 of the Fast-track Approvals Act 2024 and, by May 2026, was in planning and design, with a fast-track consent application lodged later in 2026.
Official: Beehive: Northport dry dock business case progressing (20 Aug 2024) Official: Kānoa / growregions: Northland shipyard and dry dock facility (updated 26 May 2026)